Reduced installation time with the Bison Weigh-In-Motion system

Installation optimization starts with site preparation

The Bison System for fast, orderly and efficient installations

When it comes to construction times, we often tend to measure efficiency by simply counting the days it takes to complete an installation. The experience gained by iWiM in the design and installation of the Bison, our system for dynamic vehicle weighing, has shown us that an efficient installation is born long before the teams arrive on site. True efficiency starts with the design.

True efficiency begins
by design.

Installing a dynamic weighing system means coordinating several activities: road works, electrical and data preparations, site infrastructure, installation of weighing sensors, positioning of equipment on the roadside, connections, configuration and testing of the system.

For this reason, one of the aspects on which we pay the most attention is the preventive definition of the activities and the timetable of the works. The different phases must be organized according to a defined sequence, identifying in advance what can – and must – be achieved before the actual installation of Bison.

Bison dynamic weighing system installed on three lanes in Argentina with heavy vehicles in transit.

Bison System Installed on Three Lanes – Argentina

Prepare your site before
to install the sensors

A fundamental principle of our working method is to arrive at the installation of weighing sensors with the site already prepared and verified. Cable ducts, manholes, power supplies, connectivity, basements, street cabinets and all other preparatory works must, as far as possible, be prepared and verified in advance.

In this way, the installation of the sensors on the roadway does not represent the beginning of a long series of subsequent processes, but becomes one of the last steps of an already organized process. Once the installation is complete, the system can be quickly connected to the prepared infrastructure, configured and put into operation.

It is this logic that allows us to approach, in the final phase of the installation, a “plug and play” approach: install, connect, configure and start weighing. The advantage is not only the reduction in time. A well-prepared construction site also means less interference between processes, fewer unforeseen events, better organization of teams and the possibility of spending more time on the activities that really matter: configuration, verification and testing of the performance of the system. For the customer, this also translates into greater predictability of activities and a reduction in interference related to the installation.

Technicians at work during the installation of the sensors of the Bisonte dynamic weighing system in Argentina.

The construction site during installation activities – Argentina

International experience

This method becomes even more important in international projects. The installations carried out in recent years in South America, Asia and Europe have confirmed how crucial it is to transfer a significant part of the work from the construction site to the preparation phase. For installations all over the world, iWiM collaborates with local partners, responsible for the preparation of the site according to the indications and technical specifications provided by iWiM technicians.

When an installation takes place thousands of kilometers from our headquarters, preventive preparation becomes essential. Before the arrival of the iWiM team, drawings, technical indications, necessary preparations and operational sequences are shared, coordinating remotely with the customer, partners and local companies. iWiM also makes its team available to support and assist the customer and partners during the installation, transferring the necessary know-how and training local technicians on the activities to be carried out, with the aim of ensuring correct execution and the best possible result.

The reduction of road closure times and the quality of the installation depend directly on careful preparation of the construction site.

The installation carried out in Argentina represents this approach well: a Bison dynamic weighing system on several lanes, for which the preparation and coordination of the activities made it possible to concentrate the presence of the iWiM team on the specialized operations of installation, connection, configuration and verification of the system.

Road construction site during the installation of the Bison dynamic weighing system on three lanes in Argentina.

Laying and installation of the Bison system – Argentina

From design to ready-to-weigh system

Bison’s quick installation therefore stems from the combination of the system’s features and the iWiM working method. Standardizing components, simplifying connections, and designing a system that can be quickly installed is essential. But to turn these features into a real advantage in the field, they need to be combined with careful planning, a clear timeline, and careful site preparation.

For us, reducing construction time does not mean working faster: it means arriving at the construction site having already done everything that could have been done before.

This is how an installation becomes simpler, tidier and faster. And above all , it is how, a few days after arriving on site, a road can have a Bison system installed, connected, tested and ready to weigh.

Bison dynamic weighing system sensors installed on the roadway in Argentina.